Do not adjust the POLine.PromisedDate out if the Requested Date is greater than Today + Additional Lead Time.

  • I would like to receive Part A and Part B at the same time.
  • Vendor1 makes both parts.
  • Vendor1 has a lead time of 7 days.
  • Part B has an additional Lead Time Value of 7 days.
  • When I enter my PO, I input a POOrder.ExpectedDate of 1 month from today. This exceeds the lead time for both Part A and Part B.
  • HOWEVER, the POLine.PromisedDate for Part B auto-populates as one month plus 7 days from today.

 

It would be helpful if Lead Time logic could take into account if the requested date within the capabilities of the lead time or not.